Date   26 February to 5 March 2019
Time   10.00 pm – 5.00 am
Duration   8 nights
Reason   To facilitate pier cap launch for the LRT3 project.

 

SHAH ALAM, 26 February 2019: MRCB George Kent Sdn Bhd (MRCBGK), the main contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be a traffic diversion on Persiaran Bukit Raja, Klang. The diversion will commence from 26 February to 5 March 2019 from 10.00 pm to 5.00 am. The closure will be deactivated during the day and traffic will resume as usual.

 

The traffic diversion is as follows:

The lanes on Persiaran Bukit Raja (Aeon Bukit Raja-bound) in front of Wisma Perkeso until Acmar office will be closed. Motorists who are heading to Aeon Bukit Raja will be diverted as indicated by the GREEN arrows in the map.

 

 

 

Motorists are reminded to exercise caution, adhere to advance warning signs and directional signage placed when travelling in this area during the construction period.

 

We apologise for any inconvenience caused to the public.

 

For public enquiries, please contact the LRT3 hotline at 1 800 18 2585.

 

–ENDS—

 

For media enquiries, please contact:

Lim Siew May
Media Manager, PR & Communications
MRCB George Kent Sdn Bhd

03-5033 6857

siewmay.lim@mrcbgk.com

 

Vanessa Song

WPC PR & Stakeholder Management

Sunway Construction Sdn Bhd

012-232 3782

vanessas@sunway.com.my

 

ABOUT MRCB GEORGE KENT (MRCBGK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4th September 2015 as the Project Delivery Partner (PDP) of the Light Rail Transit 3 (LRT3).

On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the contractor.

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest homegrown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3)

The LRT3 envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3

-->
Translate »