Date   4 March 2019 to 31 May 2019
Time   Monday to Saturday             : 9:00 a.m. to 6:00 p.m.                                                

                                                              : 11:00 p.m to 5:00 a.m

                                                              (Night time construction activities)

 Sunday and Public Holiday : No construction activities

Duration   3 months
Reason   To facilitate LRT3 bored piling works on Persiaran Kerjaya Off Jalan Pengaturcara U1/51

 

SHAH ALAM, SELANGOR – 4 March 2019: MRCB George Kent, the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be a temporary T-junction closure and traffic diversions at the current road closure along Persiaran Kerjaya.

The temporary T-junction closure and traffic diversions will occur Off Jalan Pengaturcara U1/51 heading towards Shah Alam and Kuala Lumpur/Subang from 4 March to 31 May 2019.

The traffic diversion is to facilitate bored piling works at the road median at the junction in front of Kawasan Perindustrian Temasya, just before Masjid An-Nur Glenmarie, Shah Alam.

During this time, motorists from Kuala Lumpur / Subang to Jalan Pengaturcara U1/51 and from Shah Alam to Jalan Pengaturcara U1/51 will be diverted as indicated in the GREEN arrows in the map below:

 

We apologise for any inconvenience caused during this project. We greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

 

For public enquiries, kindly contact the LRT3 hotline at 1 800 18 2585.

 

–ENDS—

 

Lim Siew May
Media Manager, PR & Communications
MRCB George Kent Sdn Bhd

03-5033 6857

siewmay.lim@mrcbgk.com

 

Salmi Azuriza Che Ali

PR & Stakeholder Management

WCT Construction Sdn Bhd

012-6546 905

salmi.azuriza@wct.my

 

 

 

ABOUT MRCB GEORGE KENT (MRCB GK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4th September 2015 as the Project Delivery Partner (PDP) of the Light Rail Transit 3 (LRT3).

On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the contractor.

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest homegrown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3)

The LRT3 envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3.

 

 

 

 

 

 

 

 

-->