Date 18 November 2020 to 19 November 2020
Day Wednesday to Thursday
Time 11:00 p.m. to 5:00 a.m.
Reason To facilitate U-Girder launching works.

 

The lane closures and traffic diversion are as shown on the map below:

 

 

The diversions are implemented following the approval from Petaling Public Works Department (JKR Petaling). Throughout the Conditional Movement Control Order (CMCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities. We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding.

 

For more information, please contact:

WL Hoon, Project Manager                                                                                                                                          : 019-6223228

Hanita Harun, PR & Stakeholder Management Manager                                                                            : 013-5755667

-->