Date 9 June 2021 to 30 September 2021
Day Monday to Sunday
Time 11:00 p.m to 5:00 a.m
Reason To facilitate Segmental Box Girder (SBG) launching and LRT3 project-related works

 

The closures and diversions are as shown on the map below:

 

Closure A from 9 June 2021 to 12 July 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Closure B from 13 July 2021 to 1 August 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

Closure C from 2 August 2021 to 30 September 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from the Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS). Throughout the Movement Control Order (MCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For more information, please contact:

Yap Kok Fong, Senior Project Manager                                                                                                                       : 012-5082908

Salmi Azuriza Che Ali, Senior Executive, PR & Stakeholder Management                                             : 012- 6546905

-->