Date 21 August 2021 to 31 October 2021
Day Monday to Sunday
Time 11:00 p.m to 5:00 a.m
Reason To facilitate Segmental Box Girder (SBG) Launching and LRT3 project-related works

 

The closures and diversions will be done in stages as shown on the maps below:

 

 

Stage 1: The leftmost lane, slow lane, and the middle lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 21 August 2021 to 10 September 2021  

 

Stage 2:  The rightmost lane, middle lane, and the slow lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 11 September 2021 to 20 September 2021.

 

Stage 3:  The rightmost lane and the middle lane (KL / Sungai Buloh-bound and Shah Alam / Subang-bound) will be closed from 21 September 2021 to 30 September 2021

 

Stage 4: The rightmost lane, middle lane and slow lane (Shah Alam / Subang-bound) will be closed from 1 October 2021 to 31 October 2021

The diversions are implemented following the approval from the Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS). Throughout the Movement Control Order (MCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For more information, please contact:

Yap Kok Fong, Senior Project Manager                                                                                                                       : 012-5082908

Salmi Azuriza Che Ali, Senior Executive, PR & Stakeholder Management                                             : 012- 6546905

-->
Translate »