Date Stage 1: 4 October 2021 to 5 October 2021

Stage 2: 6 October 2021 to 9 October 2021

Stage 3: 10 October 2021 to 14 October 2021

Stage 4: 15 October 2021 to 22 October 2021

Day Monday to Sunday
Time Phase 1: 10:00 p.m. to 1:00 a.m. – Pandamaran Interchange (Ramp A – Kuala Lumpur bound)

Phase 2: 1:00 a.m. to 5:00 a.m – KM18.6 to KM19.1 of SAE (East bound)

Reason To facilitate ‘Segmental Box Girder’ (SBG) launching and LRT3 project-related works

 

The closures and traffic diversions are indicated on the maps below.

 

 

Stage 1: Fast lane closure at the Pandamaran Interchange (Ramp A) from Jalan Langat (Kuala Lumpur bound), 10:00 p.m. to 1:00 a.m., followed by a slow lane closure at KM18.5 to KM19.1 of SAE (East bound), 1:00 a.m. to 5:00 a.m. from 4 October 2021 to 5 October 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 2: Full closure of Ramp A (Kuala Lumpur bound), 10:00 p.m. to 1:00 a.m., followed by a slow lane closure at KM18.5 to KM19.1 of SAE (East bound), 1:00 a.m. to 5:00 a.m. from 6 October 2021 to 9 October 2021

 

 

 

 

 

 

 

 

 

 

 

 

Stage 3: Full closure of Ramp A (Kuala Lumpur bound), 10:00 p.m. to 1:00 a.m., followed by slow and middle lane closures at KM18.5 to 19.1 of SAE (East bound), 1:00 a.m. to 5:00 a.m. from 10 October 2021 to 14 October 2021

 

 

 

Stage 4: Full closure of Ramp A (Kuala Lumpur bound), 10:00 p.m. to 1:00 a.m., followed by full closure at KM18.5 to 19.1 of SAE (East bound), 1:00 a.m. to 5:00 a.m.

from 15 October 2021 to 22 October 2021

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from IPD Klang Selatan (PDRM), the Klang Public Works Department (JKR Klang), Klang Municipal Council (MPK), Shah Alam Expressway – SAE (KESAS), and Malaysian Highway Authority (MHA). Throughout the National Recovery Plan (NRP) Phase 2 period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

Motorists are advised to drive carefully and follow the traffic signage. We apologise for any inconvenience caused to the SAE (KESAS) users.

For more information, please contact :

En. Nor Azri Omar, Project Director                                                                                                                     : 012 – 320 5736

En. Salleh Sani, Senior Manager, PR & Stakeholder                                                                                      : 019 – 253 0282

-->