Date 18 November 2021 to 31 January 2022
Day Monday to Sunday
Time 11:00 p.m to 5:00 a.m
Reason To facilitate Segmental Box Girder (SBG) Launching and LRT3 project-related works

 

The closures and diversions will be done in stages as shown on the maps below:

 

Stage 1: The leftmost lane and slow lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 18 November 2021 to 25 December 2021.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 2:  The rightmost lane and middle lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 26 December 2021 to 15 January 2022.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 3:  The rightmost lane and the middle lane (KL / Sungai Buloh-bound and Shah Alam / Subang-bound) will be closed from 16 January 2022 to 31 January 2022.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from the Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS). Throughout the National Recovery Plan (NRP) Phase 4, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For more information, please contact: