Media Release: intermittent closures at the Pandamaran Interchange (Ramp A) from Jalan Langat heading to Kuala Lumpur, (Ramp B) from Kuala Lumpur heading to Jalan Langat and from KM18.5  to KM19.1 (both bounds) of the Shah Alam Expressway – SAE (KESAS) to facilitate Long Span launching and LRT3 project-related works from 17 November 2021 to 22 December 2021

 SHAH ALAM, SELANGOR – 14 November 2021: Setia Utama LRT 3 Sdn Bhd (formerly known as MRCB George Kent Sdn Bhd (MRCBGK)), the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be intermittent closures at the Pandamaran Interchange (Ramp A) from Jalan Langat heading to Kuala Lumpur, (Ramp B) from Kuala Lumpur heading to Jalan Langat and from KM18.5  to KM19.1 (both bounds) of the Shah Alam Expressway – SAE (KESAS) to facilitate Long Span launching and LRT3 project-related works from 17 November 2021 to 22 December 2021, 10:00 p.m. to 6:00 a.m. in the following stages:

 

Stage 1: Fast lane closure from KM19.1 to KM18.5 of SAE (West bound) and middle and fast lane closure from KM18.5 to KM19.1 (East bound), 10:00 a.m. to 6.00 a.m. from 17 November 2021 to 22 November 2021.

During the closure, the traffic management scheme will be as shown on the map below:

 

  

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 2: Full closure of Ramp B from SAE heading to Jalan Langat (Banting bound), 10:00 p.m. to 6:00 a.m. from 6 December 2021 to 7 December 2021.

During the closure, the traffic management scheme will be as indicated on the map below:

 

 

 

 

 

 

 

 

 

 

 


 

 

 

Stage 3: Full closure of Ramp B from SAE heading to Jalan Langat (Klang bound), 10:00 p.m. to 6:00 a.m. from 8 December 2021 to 11 December 2021.

During the closure, the traffic management scheme will be as indicated on the map below:


 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 4: Full closure from KM19.1 to KM18.5 of SAE (West bound), 10:00 p.m. to 6:00 a.m. from 12 December 2021 to 13 December 2021.

During the closure, the traffic management scheme will be as indicated on the map below:


 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 5: Full closure from KM18.5 to KM19.1 of SAE (East bound), 10:00 a.m. to 6:00 a.m., from 14 December 2021 to 18 December 2021.

During the closure, the traffic management scheme will be as indicated on the map below:

 

 


 

 

 

 

 

 

 

 

 

 

 

Stage 6: Full closure of Ramp A from Jalan Langat heading onto SAE (Kuala Lumpur bound), 10:00 p.m. to 6:00 a.m. from 19 December 2021 to 22 December 2021.

During the closure, the traffic management scheme will be as indicated on the map below:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from IPD Klang Selatan (PDRM), the Klang Public Works Department (JKR Klang), Klang Municipal Council (MPK), Shah Alam Expressway (KESAS) and Malaysian Highway Authority (MHA).

Throughout the National Recovery Plan (NRP) Phase 4 period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities. Motorists are advised to drive carefully and follow the traffic signages during the closure. We apologise for any inconvenience caused to the SAE (KESAS) users.

For enquiries, please contact the LRT3 helpline at 1 800 18 2585.

 

-ENDS-

 

For media enquiries, please contact:

Lim Siew May

Media Manager, PR & Communications

Setia Utama LRT 3 Sdn Bhd

(Formerly known as MRCB George Kent Sdn Bhd)

03-5033 6857

siewmay.lim@mrcbgk.com

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3) PROJECT

The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3

-->
Translate »