Date 17 November 2021 to 22 December 2021
Day Monday to Sunday
Time 10:00 p.m. to 6:00 a.m.
Reason To facilitate Long Span launching and LRT3 project-related works

 

The intermittent closures and traffic diversions are as indicated on the maps below:

 

Stage 1: Fast lane closure from KM19.1 to KM18.5 of SAE (West bound) and middle and fast lane closure from KM18.5 to KM19.1 (East bound), 10:00 p.m. to 6.00 a.m. from 17 November 2021 to 22 November 2021.

 

 


 

 

 

 

 

 

 

 

 

 

 

 

Stage 2: Full closure of Ramp B from SAE heading onto Jalan Langat (Banting bound), 10:00 p.m. to 6:00 a.m. from 6 December 2021 to 7 December 2021.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 3: Full closure of Ramp B from SAE heading onto Jalan Langat (Klang bound), 10:00 p.m. to 6:00 a.m. from 8 December 2021 to 11 December 2021.

 

 


 

 

 

 

 

 

 

 

 

 

 

 

Stage 4: Full lane closure from KM19.1 to KM18.5 of SAE (West bound), 10:00 p.m. to 6:00 a.m. from 12 December 2021 to 13 December 2021.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 5: Full lane closure from KM18.5 to KM19.1 of SAE (East bound), 10:00 p.m. to 6:00 a.m., from 14 December 2021 to 18 December 2021.

 

 


 

 

 

 

 

 

 

 

 

 

 

 

Stage 6: Full closure of Ramp A from Jalan Langat heading onto SAE (Kuala Lumpur bound), 10:00 p.m. to 6:00 a.m. from 19 December 2021 to 22 December 2021.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from IPD Klang Selatan (PDRM), the Klang Public Works Department (JKR Klang), Klang Municipal Council (MPK), Shah Alam Expressway (KESAS), and Malaysian Highway Authority (MHA). Throughout the National Recovery Plan (NRP) Phase 4 period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

Motorists are advised to drive carefully and follow the traffic signage. We apologise for any inconvenience caused to the SAE (KESAS) users.

For more information, please contact :

En. Nor Azri Omar, Project Director                                                                                                                     : 012 – 320 5736

En. Salleh Sani, Senior Manager, PR & Stakeholder                                                                                     : 019 – 253 0282

-->