Date 7 February 2022 to 1 March 2022
Day Monday to Sunday
Time 11:00 p.m. to 5:00 a.m.
Reason To facilitate LRT3 project-related works

 

The various stages’ lane closures and traffic diversions are as shown on the map below:

 

Stage 1: The leftmost lane on Persiaran Kerjaya (Shah Alam-bound) will be closed from 7th February 2022 to 21st February 2022

 

Stage 2: The rightmost lane on Persiaran Kerjaya (Shah Alam-bound) will be closed from 8th February 2022 to 22nd February 2022


 

 

Stage 3: Both lanes heading towards Jalan Lapangan Terbang Subang will be closed from 9th February 2022 to 23rd February 2022

 

 

 

 

Stage 4: The rightmost lane on Persiaran Kerjaya and leftmost lane on Jalan Lapangan Terbang Subang will be closed from 10th February 2022 to 24th February 2022

 

 

  

Stage 5: Two (2) lanes on Jalan Lapangan terbang Subang heading towards Kuala Lumpur will be closed from 11st February 2022 to 25th February 2022

 

 

Stage 6: Two (2) lanes heading towards Lapangan Terbang Subang will be closed from 12nd February 2022 to 26th February 2022

 

 

 

Stage 7: The rightmost lane heading towards Lapangan Terbang Subang and two lanes heading towards Federal highway will be closed from 13th February 2022 to 27th February 2022

 

 

 

Stage 8: Three (3) lanes heading towards Kuala Lumpur will be closed 14th February 2022 to 28th February 2022

 

 

 

 

Stage 9: Both lanes heading towards Jalan Lapangan Terbang Subang will be closed from 15th February 2022 to 01st March 2022

The diversions are implemented following the approval from the Jabatan Kerja Raya Daerah Petaling (JKR Petaling) and Majlis Bandaraya Petaling Jaya (MBPJ). Throughout the National Recovery Plan (NRP) Phase 4 period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

 

For more information, please contact:

Ahmad Asraf Ramadhan, Project Manager                                                                                                                    : 017-9163212

Mohd Hanifah bin Harun, Project Coordinator                                                                                                           : 013-7351817

-->