On 07 Dec 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a pre-qualification tender briefing for the Bumiputera Contractors with CIDB G2 to G4 for “small work packages comprising of but are not limited to areas such as surface works, mechanical & engineering works, concrete works, external architectural works and interior fittings out works for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Dato’ Moktar Samad, Yang Dipertua Persatuan Kontraktor Melayu Malaysia, Mr. Zurin Bin Zubir, Secretary, Contractor and Entrepreneur Development Division (BPKU) of Ministry of Works, Puan Zalina Mat, Manager, Construction Industry Development Board (CIDB), Mr. Muhammad Nazrin Saadon, Branch Manager, Credit Guarantee Corporation (CGC) Malaysia and Mr. Ahmad Nizam Mohamed Amin, Chief Infra Services Officer, Prasarana.
Event GalleryOn 22 Nov 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “construction and completion of bus depot, ancillary buildings and other associated works for packages BSD (E,W1 & W2) for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Shafie Hairi, SVP PRAISE, Mr. Mohd. Yusri Jamaludin, Manager, IED, MRCBGK, Mr. Thinakaran, Manager, Environmental, Safety & Health (ESH), MRCBGK, Mr. Rosli Yaacob, Manager, Quality Assurance & Quality Control (QAQC), MRCBGK, Mr. Muhammad Zarul Mohd. Sukri, Executive, PR & Communications, MRCBGK and Mr. Muhammad Firdaus, Manager Contracts, MRCBGK.
Event GalleryOn 20 September 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held three tender briefings, namely for the:
Present at the briefings were:
Event Gallery
On 13 September 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supervising consultant land surveyor services for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Ismail Shah Putra Samin, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Mohd Tarmizi Othman, Surveyor, Infrastructure Construction Management, MRCBGK and Mr. Winston Lam Kah Khoon, Manager, Contracts Management, MRCBGK.
Event GalleryOn 23 August 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery and installation of low voltage transformer for package LVT for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mdm. Nurul Rasyidah Mislan, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Captain Noor Azmi Sharif, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Ms. Mas Ayu Binti Mohd Yusof, Senior Engineer, Infrastructure Construction Management, MRCBGK; Mr. Rosli Yaacob, Manager, Quality Assurance and Quality Control (QAQC), MRCBGK and Mr. Ahmad Qaramil Suwardi, Executive, Contracts Management, MRCBGK.
On 23 August 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery and installation of door and ironmongery for package DIR (E&W) for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Rahizad Rashid, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Captain Noor Azmi Sharif, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Mohd Yusri Jamaludin, Manager, Infrastructure Engineering & Design Management, MRCBGK; Mr. Rosli Yaacob, Manager, Quality Assurance and Quality Control (QAQC), MRCBGK and Mr. Ahmad Qaramil Suwardi, Executive, Contracts Management, MRCBGK.
Event GalleryOn 2 August 2017, Prasarana Malaysia Berhad (Prasarana), MRCB George Kent Sdn Bhd (MRCBGK) and the CRRC Zhuhou Locomotive Co Ltd (CRRC ZELC) – Siemens Limited China – Tegap Dinamik Sdn Bhd consortium held a ceremony on the signing of the LRT3 Light Rail Vehicles (LRV) work package. The event was attended by Mr. Huang Huikang, Ambassador of the People’s Republic of China in Malaysia; Tan Sri Ismail Adam, Chairman, Prasarana Group; Dato’ Sri Azmi Abdul Aziz, Group President and Chief Executive Officer, Prasarana; Mr. Ong Gin Lip, Project Director, MRCBGK; Mr. Liu Hualong, Chairman, CRRC Corporation Limited; Mr. Lothar Herrmann, President and Chief Executive Officer, Siemens Limited China and Mr. Ahmad Lazri bin Long Ahmad, Managing Director, Tegap Dinamik Sdn Bhd. An estimated 150 guests attended the event, comprising of Prasarana and MRCBGK’s employees, as well as members of the media. The launch began with a speech by Mr. Lothar Herrmann, President and Chief Executive Officer, Siemens Limited China, followed by a speech by Mr. Liu Hualong, Chairman, CRRC Corporation Limited, and a speech by Prasarana’s Group Chairman, Tan Sri Ismail Adam. The event further witnessed the official signing of the documents.
Event GalleryOn 12 July 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery and installation of bridge bearing Eastern & Western packages for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mdm. Nurul Rasyidah Mislan, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Mohd Zaidi Mat Seman, Senior Engineer, Infrastructure Construction Management, MRCBGK; Captain Noor Azmi Sharif, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK and Mr. Ahmad Qaramil Suwardi Executive, Contracts Management, MRCBGK.
Event GalleryOn 21 June 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the “design, construction and completion of underground tunnel, stations, ancillary buildings and other associated works for the underground package for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mdm. Nurul Rasyidah Mislan, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Mohd Nor Nahar Abdul Hadi, Senior Engineer, Infrastructure Construction Management, MRCBGK; Captain Noor Azmi Sharif, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts Management, MRCBGK; Ms. Liyana Yusoff, Manager, Strategic Communications, MRCBGK; Mr. Rosli Yaacob, Manager, Quality Assurance and Quality Control (QAQC), MRCBGK; Ms. Wan Nur Ainaa, Executive, Technology Depository Agency and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 14 June 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing (retender exercise) for the “design, manufacture, supply, delivery, installation, testing and commissioning of trackwork and power conductor rail for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. George Josef Pauli, Deputy Project Director – System, MRCBGK; Mdm. Faith Tiong, Senior Manager, Contracts Management, MRCBGK; Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana and Ms. Nor Muliati Awatif Norazman, representative of Industrial Collaboration Programme (ICP), Prasarana.
Event GalleryOn 25 May 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery, installation, testing and commissioning of escalators for package ESC (Eastern & Western) for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Rahizad Rashid, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Chan Wai Loon, Design Engineer, Infrastructure, Engineering & Design Department (IED), MRCBGK; Mr. Thong Chong Yong, Senior Manager, Contracts Management, MRCBGK and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 25 May 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the LRT3’s “supply, delivery, installation, testing and commissioning of lifts for package LIF (Eastern & Western) for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Yazid Ahad, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Chan Wai Loon, Design Engineer, Infrastructure, Engineering & Design Department (IED), MRCBGK; Mr. Mohd Salahuddin Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Thong Chong Yong, Senior Manager, Contracts Management, MRCBGK and Mr. Ravendran Rasalingam, General Manager, Quality Assurance and Quality Control (QAQC), MRCBGK.
Event GalleryOn 24 May 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery, installation, testing and commissioning of air conditioning and mechanical ventilation system for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Rahizad Rashid, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Fadli Naim Md Yusop, Engineer, Infrastructure Construction Management, MRCBGK; Mr. Mohd Salahuddin Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Thong Chong Yong, Senior Manager, Contracts Management, MRCBGK and Mr. Ravendran Rasalingam, General Manager, Quality Assurance and Quality Control (QAQC), MRCBGK.
Event GalleryOn 24 May 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery, installation, testing and commissioning of genset for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Ahmad Hakimi Ali, Associate, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Ahmad Ruzaini Redzuan, Engineer, Infrastructure Construction Management, MRCBGK; Mr. Mohd Salahuddin Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Thong Chong Yong, Senior Manager, Contracts Management, MRCBGK and Mr. Ravendran Rasalingam, General Manager, Quality Assurance and Quality Control (QAQC), MRCBGK.
Event GalleryOn 24 May 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “supply, delivery, installation, testing and commissioning of fire protection system (Eastern & Western) for Light Rail Transit 3 (LRT3) from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Yazid Ahad, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Mohamad Hazlay Hashim, Senior Engineer, Infrastructure Construction Management, MRCBGK; Mr. Mohd Salahuddin Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Thong Chong Yong, Senior Manager, Contracts Management, MRCBGK and Mr. Ravendran Rasalingam, General Manager, Quality Assurance and Quality Control (QAQC), MRCBGK.
Event GalleryOn 3 May 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, ancillary buildings and other associated works for package GS01 from Bandar Utama – Johan Setia”. Present at the briefing were Tuan Haji Khairani Mohamed, Chief Executive Officer, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Ir. Ahmad Nizam Mohamed Amin, Chief Infra Services Officer, Prasarana; Mr. Mohamed Ibrahim Packeer Mohamad, Head of LRT3, PRAISE; Mr. Ong Gin Lip, Project Director, MRCBGK; Mdm Nurul Rasyidah Mislan, Vice President, PRAISE; Mr. Leau Poh Bin, Project Manager, Infrastructure Construction Management, MRCBGK; Captain Noor Azmi Bin Sharif, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Rosli Yaacob, Manager, Quality Assurance and Quality Control (QAQC), MRCBGK; Ms. Liyana Yusoff, Manager, Strategic Communications, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts Management, MRCBGK and Mdm. Nur Mulliati, representative,Technology Depository Agency.
Event GalleryOn 26 April 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, ancillary buildings and other associated works for package GS09 from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Yazid Ahad, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr.Syahmeir Rangkuti Ishak , Manager, Infrastructure Construction Management, MRCBGK; Major Mohd Salahuddin Haji Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Ravendran Rasalingam, General Manager, Quality Assurance and Quality Control (QAQC), MRCBGK; Mr. Ravindran Raman Kutty, General Manager, Strategic Communications, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts Management, MRCBGK; Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana and Major Kamarul Azhan Nordin, Program Director, Technology Depository Agency.
Event GalleryFrom 10th April 2017 till 23rd April 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held the LRT3’s Public Information Update to inform members of the public on the final changes to the LRT3 stations and its alignment. The event was held at seven locations, namely at the Land and Public Transport Commission’s (SPAD) office; Kelana Square; CGC-Glenmarie LRT station; Giant hypermarket, Shah Alam; Klang Parade; Klang Municipal Council’s (MPK) office and AEON Bukit Tinggi.
Our booths at the seven locations was visited by 1347 members of the public. Relevant materials related to the alignment and station changes were prepared consisting of drawings of Plan and Profile, Site Station Context and the benefits of each locations, to ensure sufficient information exhibited to the public.
The changes involved Station 6, Station 7, Station 11, Station 19, Station 21 and Station 26.
Station 7’s proposed location was originally encroaching Tenaga Nasional Berhad’s (TNB) Transmission Main Intake (PMU) area. The new alignment has been shifted away from the TNB pylon to provide greater safety to the LRT3 commuters. The adjusted alignment will also avoid the relocation work of the existing TNB PMU and avoid utilities services disruption to the nearby commercial and residential areas.
Station 11 will be LRT3’s only underground station upon completion. The initial construction method for the underground section is the “Cut and Cover” method. Upon further studies, the construction method for Station 11 has been replaced with the Tunnel Boring Machine (TBM) method. The TBM method reduces the likelihood of encountering building foundations or otherwise damaging existing structures during construction. It also reduces disturbance to the surrounding soil, reduces ventilation requirements, improves personnel safety and results in faster working speed. The new construction method will also reduce the need for major traffic diversion and allows for the preservation of matured trees along Persiaran Hishamuddin.
Station 19’s location has been shifted 130 meters before Jalan Pulau Pinang 1 and the junction of Jalan Murai. The original proposed location was opposite the BHP gas station and on the junction of Jalan Kelicap 49.The new location of Station 19 will also have three entrances from the north and south bound of Jalan Meru to accommodate for more commuters within the area. It was also shifted away from the BHP petrol station in order to ensure the safety of the public within the area. As the new location is away from the road junction, inconvenience towards road users can be significantly reduced.
Station 21’s original alignment was encroaching into the Kuan Yin temple boundary, an area gazetted as a national heritage. The new alignment has been shifted to the slip road before Bulatan Simpang Lima to avoid any impact towards the heritage building and the area surrounding it. The new alignment location will also reduce the impact of traffic congestion to the road users.
Station 26 has been shifted from Jalan Klang Banting’s junction towards Jalan Langat to reduce traffic inconvenience to the road users. The new station location is also nearer to the multi-storey level carpark which provides ease and comfort to the commuters of LRT3. Additionally, the new location will allow provision for additional train entry access and exits to the LRT3’s depot where maintenance and service of the light rail vehicles will be carried out.
The two weeks event also received comments and feedback from the visitors.
Event GalleryOn 19 April 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, ancillary buildings and other associated works for package GS06 from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Rahizad Rashid, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Mohd Rafie Ahmad, Senior Engineer, Infrastructure Construction Management, MRCBGK; Major Mohd Salahuddin Haji Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Rosli Yaacob, Manager, Quality Assurance and Quality Control (QAQC), MRCBGK; Ms. Sharifah Naemah Alsagoff, Executive, Strategic Communications, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts Management, MRCBGK; Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana and Major Kamarul Azhan Nordin, Program Director, Technology Depository Agency.
Event Gallery
On 14 April 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “design, manufacture, supply, delivery, installation, testing and commissioning of electronic access control system for Light Rail Transit 3 (LRT3) project from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Mohamed Ibrahim Packeer Mohamad, Head of LRT3, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Ong Gin Lip, Project Director, MRCBGK; Mdm. Azirinda Mohd Sultan, Vice President, PRAISE; Mr.Teoh Khah Wah, Senior Manager, System, MRCBGK; Mr. Ravendran Rasalingam, General Manager, Quality Assurance and Quality Control (QAQC), MRCBGK; Major Mohd Salahuddin Haji Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mdm. Faith Tiong, Senior Manager, Contracts Management, MRCBGK and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 12 April 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, Iconic Bridge, park and ride, ancillary buildings and other associated works for package GS02 from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Ong Gin Lip, Project Director, MRCBGK; Mdm. Nurul Rasyidah Mislan, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Leau Poh Bin, Project Manager, Infrastructure Construction Management, MRCBGK; Captain Noor Azmi Sharif, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts Management, MRCBGK; Mr. Naresh Kumarasamy, Manager, Quality Assurance and Quality Control (QAQC), MRCBGK; Mr. Ravindran Raman Kutty, General Manager, Strategic Communications, MRCBGK; Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana and Mdm. Idayati Alek, representative, Industrial Collaboration Programme (ICP), Prasarana.
Event GalleryOn 5th April 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, ancillary buildings, and other associated works for package GS04 from Bandar Utama – Johan Setia”. Present at the briefing were Tuan Haji Khairani Mohamed, Chief Executive Officer, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Ir. Ahmad Nizam Mohamed Amin, Chief Infra Services Officer, Prasarana; Mr. Mohamed Ibrahim Packeer Mohamad, Head of LRT3, PRAISE; Mr. Ong Gin Lip, Project Director, MRCBGK; Mdm Nurul Rasyidah Mislan, Vice President, PRAISE; Mr. Nor Nasyriq Shahirudin, Manager, Civil & Structural, Infrastructure Construction Management, MRCBGK; Major Mohd Salahuddin Haji Yaacob, Senior Manager, Enviromental, Safety & Health (ESH), MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts, Contracts Management, MRCBGK; Mr. Naresh Kumarasamy, Manager, QAQC; Ms. Liyana Yusoff, Manager, Strategic Communications, MRCBGK and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 30th March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the “design, manufacture, supply, delivery, installation, testing and commissioning of automatic fare collection system for Light Rail Transit 3 (LRT3) project from Bandar Utama – Johan Setia”. Present at the briefing were Tuan Haji Khairani Mohamed, Chief Executive Officer, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Ir. Ahmad Nizam Mohamed Amin, Chief Infra Services Officer, Prasarana; Mr. Mohamed Ibrahim Packeer Mohamad, Head of LRT3, PRAISE; Mr. Ong Gin Lip, Project Director, MRCBGK; Mr. Baser Abdul Ghani, Senior Vice President, PRAISE; Mr. George Josef Pauli, Deputy Project Director – System, MRCBGK; Major Mohd Salahuddin Haji Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mdm. Faith Tiong, Senior Manager, Contracts, Contracts Management, MRCBGK; Mr. Ravendran Rasalingam, General Manager, QAQC; Major Kamarul Azhan Nordin, Program Director, Technology Depository Agency and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 29th March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, ancillary buildings, and other associated works for package GS05 from Bandar Utama – Johan Setia”. Present at the briefing were Tuan Haji Khairani Mohamed, Chief Executive Officer, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Ir. Ahmad Nizam Mohamed Amin, Chief Infra Services Officer, Prasarana; Mr. Mohamed Ibrahim Packeer Mohamad, Head of LRT3, PRAISE; Mr. Ong Gin Lip, Project Director, MRCBGK; Mdm Nurul Rasyidah Mislan, Vice President, PRAISE; Mr. Noor Azlan Salleh, General Manager, Infrastructural Construction, MRCBGK; Major Mohd Salahuddin Haji Yaacob, Senior Manager, Environmental, Safety & Health (ESH), MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts, Contracts Management, MRCBGK; Mr. Ravendran Rasalingam, General Manager, QAQC; Ms. Liyana Yusoff, Manager, Strategic Communications, MRCBGK; Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana and Ms. Nur Sukriyah Mohd Tarmizi, Associate, Industrial Collaboration Programme (ICP), Prasarana.
Event GalleryOn 22nd March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, Iconic Bridge, park and rides, ancillary buildings, and other associated works for package GS10 from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Ong Gin Lip, Project Director, MRCBGK; Mr. Henny Shahril Kasiran, Senior Vice President, Prasarana; Mr. Syahmeir Rangkuti Ishak, Manager, Civil & Structural, Infrastructure Construction Management, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts, Contracts Management, MRCBGK; Mr. Ravendran Rasalingam, General Manager, QAQC, Mr. Ravindran Raman Kutty, General Manager, Strategic Communications, MRCBGK and Ms. Nur Sukriyah Mohd Tarmizi, Associate, Industrial Collaboration Programme (ICP), Prasarana.
Event GalleryOn 22nd March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, Iconic Bridge, park and rides, ancillary buildings, and other associated works for package GS03 from Bandar Utama – Johan Setia”. Present at the briefing were Mr. Ong Gin Lip, Project Director, MRCBGK; Mr. Henny Shahril Kasiran, Senior Vice President, Prasarana; Mr. Nor Nasyriq Shahirudin, Manager, Civil & Structural, Infrastructure Construction Management, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts, Contracts Management, MRCBGK; Mr. Ravendran Rasalingam, General Manager, QAQC; Mr. Ravindran Raman Kutty, General Manager, Strategic Communications, MRCBGK and Ms. Nur Sukriyah Mohd Tarmizi, Associate, Industrial Collaboration Programme (ICP), Prasarana.
Event GalleryOn 15th March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of guideway, stations, Iconic Bridge, park and rides, ancillary buildings, and other associated works for package GS07 – GS08 for LRT3 Bandar Utama – Johan Setia”. Present at the briefing were Mr. Ong Gin Lip, Project Director, MRCBGK; Mr. Henny Shahril Kasiran, Senior Vice President, Prasarana; Tuan Haji Mohamad Amjad Faruq, Deputy Project Director – Infrastructure, MRCBGK; Mr. Kalaiselvan Selvaraja, General Manager, Safety, Security, Health & Envrionmental, Support Group, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts, Contracts Management, MRCBGK; Mr. Naresh Kumarasamy, Manager, QAQC and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 9th March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the LRT3’s “advance work packages – design and build of installation, testing and commissioning of gas pipes relocation works for LRT3 Bandar Utama – Johan Setia”. Present at the briefing were Mr. Yazid Ahad, Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE), Mr. Norzaidri Abdullah, Senior Manager, Infrastructural Construction, Interfaces & Integration Management, MRCBGK and Mr. Mohd Hanif Izwan, Senior Executive, Contracts, Contracts Management, MRCBGK.
Event GalleryOn 7th March 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the LRT3’s “tender calling schedule session for packages GS of LRT3 Bandar Utama – Johan Setia”. Present at the briefing were Tuan Haji Mohamed Ibrahim Packeer Mohamed, Head of LRT3, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE) and Mr. Ong Gin Lip, Project Director of LRT3, MRCBGK.
Event GalleryOn 27th February 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing and site visit for the LRT3’s “construction and completion of Johan Setia depot (Phase 2) and associated works for LRT3 Bandar Utama – Johan Setia”. Present at the briefing were Mr. Shafie Hairie, Senior Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Noor Azlan Salleh, General Manager, Infrastructural Construction, MRCBGK; Mr. Ravendran Rasalingam, General Manager, QAQC, MRCBGK; Mr. Wong Tze Song, Senior Manager, Contracts, MRCBGK and Mr. Noeh Niqmann Zainal Abidin, certified integrity officer, Prasarana.
Event GalleryOn 4th February 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held the prize giving ceremony for LRT3’s “Painting The Rail Future” art contest. The event was held at the Glenmarie LRT Station and was attended by, Dato’ Sri Azmi bin Abdul Aziz, President & Group CEO, Prasarana;Ybhg. Dato’ Sri Ir. Dr Judin bin Abdul Karim, Chairman, MRCBGK; Tuan Haji Khairani Mohamed, CEO, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE) and Mr.Ong Gin Lip, Project Director, MRCBGK.
An estimated 100 pax of guests arrived at the distinguished event, comprising of the 12 winners as well as their family members, Prasarana employees and members of the media. The launch begins with the sharing of the background of the “Painting The Rail Future” art contest, followed by a video presentation on the LRT3 project. The event was further celebrated by a welcome address by Dato’ Sri Azmi bin Abdul Aziz and the announcement of winners. The event ended with a group photography session.
Event GalleryOn 3rd February 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the LRT3’s “design, manufacture, supply, delivery, installation, testing and commissioning of depot equipment and maintenance vehicles for LRT3 Bandar Utama – Johan Setia”. Present at the briefing were Mr. Abdul Baser Abdul Ghani, Senior Vice President, Prasarana Rail and Infrastructure Projects Sdn Bhd (PRAISE); Mr. Liaw Chong Beng, General Manager, Systems, Engineering & Design, MRCBGK; Mr. Ravendran Rasalingam, General Manager, QAQC, MRCBGK; Mdm Faith Tiong, Senior Manager, Contracts, MRCBGK and Mr. Kamarul Azhan Nordin, Programme Director, Industrial Collaboration Programme (ICP), Prasarana.
Event GalleryOn 12th January 2017, Prasarana Malaysia Berhad (Prasarana) and MRCB George Kent Sdn Bhd (MRCBGK) held a tender briefing for the LRT3’s “design, manufacture, supply, delivery, installation, testing and commissioning of track works and power conductor rail for LRT3 Bandar Utama – Johan Setia”. Present at the briefing was Mr. Abdul Baser Abdul Ghani, Senior Vice President, Prasarana Rail and Infrastructure Projects Sdn. Bhd (PRAISE); Mr. Ong Gin Lip, Project Director, MRCBGK; Mr. George Josef Pauli, Deputy Project Director- System, MRCBGK; Mr. Kamarul Azhan Nordin, Programme Director, Industrial Collaboration Programme (ICP), Prasarana and Mdm. Faith Tiong, Senior Manager – Contracts, MRCBGK.
Event Gallery