Date | 4 – 6 March 2019 |
Time | 10.00 pm – 5.00 am |
Duration | 3 days |
Reason | Temporary road closures on Jalan Klang-Banting to dismantle the existing conductor of TNB pylon and to replace it with a new one for the LRT3 project. |
KLANG, SELANGOR – 1 March, 2019: MRCB George Kent, the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be temporary road closures on Jalan Klang – Banting to dismantle the existing conductor of TNB pylon on Jalan Klang – Banting from 4 – 6 March 2019.
The closures, which will commence from 10:00 a.m. until 4:00 p.m. from Monday to Sunday, will be implemented at a 10-minute interval.
The closures are as shown in the map below:
Traffic will be controlled by flagmen and police traffic who will be stationed at the allocated points, subject to weather conditions. Directional signages will also be displayed during the closures.
The road closures will only take place during the time period stated above.
We apologise for any inconvenience caused to the public.
For public enquiries, please contact the LRT3 hotline at 1 800 18 2585.
–ENDS–
For media enquiries, please contact:
Lim Siew May
Media Manager, PR & Communications
MRCB George Kent Sdn Bhd
03-5033 6857
Mohd Hanifah Bin Harun
Public Relation & Stakeholder Management
Huls Transmission Sdn Bhd
013-7351817
hanifharun_htsb@yahoo.com
ABOUT MRCB GEORGE KENT (MRCBGK)
MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4 September 2015 as the Project Delivery Partner (PDP) of Light Rail Transit 3 (LRT3).
On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the contractor.
MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest homegrown railway system specialist in Malaysia.
MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.
ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3) PROJECT
The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3