SHAH ALAM, SELANGOR – 25 April 2019: MRCB George Kent Sdn Bhd (MRCBGK), the contractor of the Light Rail Transit 3 (LRT3) project wishes to inform the public that its work package contractor (WPC) Pembinaan Jaya Zira Bhd is extending the hours of the lane closure and traffic diversion in front of Vonza Sdn Bhd, Jalan Langat, Klang to facilitate utilities relocation works for the LRT3 project.

Originally, the lane closure and traffic diversion were supposed to start from 10 p.m. to 6 a.m. from 26 April 2019 until 27 April 2019. However, the hours have now been extended on 27 April 2019. Our WPC will work continuously from 10:00 p.m. (Friday, 26 April 2019) until 4:00 p.m (Saturday, 27 April 2019).

Our WPC discovered a hard ground unexpectedly during excavation works on 24 April 2019. Hence, more time is required to excavate and lay the water pipe. The new schedule still falls within the approved hours of Jabatan Kerja Raya (JKR).

During the temporary lane closure which has been approved by Jabatan Kerja Raya (JKR), motorists on Jalan Langat heading towards Klang are reminded to exercise caution and adhere to advance warning signs as indicated by the map below:

 

 

 

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For public enquiries, kindly contact the LRT3 hotline at 1 800 18 2585.

 

–ENDS—

 

 

For media enquiries, please contact:

Lim Siew May
Media Manager, PR & Communications
MRCB George Kent Sdn Bhd
03-5033 6857
siewmay.lim@mrcbgk.com

 

Raja Nazhatul Shima binti Raja Abdul Aziz
Manager, PR & Stakeholders
Pembinaan Jaya Zira Sdn Bhd
010-5597979
shima@pjzsb.com

 

ABOUT MRCB GEORGE KENT (MRCBGK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4 September 2015 as the Project Delivery Partner (PDP) of Light Rail Transit 3 (LRT3).

On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the contractor.

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest home grown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3) PROJECT

The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity

to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3.

-->