Date

 27 November 2019 to 10 December 2019

Day

 Monday to Saturday

Time

 10:00 a.m. to 5:00 p.m.

Reason 

 To facilitate Telekom Malaysia cable relocation works on Jalan Kerjaya at the entrance of Temasya Anggun residential area for the LRT3 project.

 

The closures are as shown on the map below:

 

The temporary closure will be done in two (2) stages, whereby once works at stage 1 are completed, works at stage 2 will follow, while one lane will be made available for motorists at all times as indicated on the maps below.

 

Stage 1

Stage 2

 

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

 

For more information, please contact:

 

WL Hoon, Project Manager                                                                                                                                          : 019-6223228

Mohd Afendi Ramli, Construction Manager                                                                                                        : 012-2993377

Hanita Harun, PR & Stakeholder Management Manager                                                                           : 013-5755667

-->