Date | 12 January 2020 to 26 February 2020 |
Day | Monday to Sunday |
Time | 24 hours |
Reason | The temporary road closure is to facilitate site clearing, earthworks, bored piling works, kentledge
block stacking works, pile cap and pier casting works and the construction of cofferdam for the LRT3 project. |
The closures and diversions are as shown on the maps below:
Closure A
Closure B
We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.
For more information, please contact:
Ong Ken Kee, Senior Project Manager : 019-6632139
Vanessa Vivekananda, Public Relations Senior Manager : 019-2835815