SHAH ALAM, SELANGOR – 13 November 2020: MRCB George Kent Sdn Bhd (MRCBGK), the main contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be intermittent road closures and traffic diversions on Persiaran Tengku Ampuan Rahimah, Klang (from before Masjid Al-Rahimiah until after Jalan Tun Abdul Razak junction, Banting and Klang town-bound), Persiaran Seraya and Jalan Sri Siantan 46 to facilitate ‘U-Girder’ launching and LRT3 project-related works from 17 November 2020 to 30 November 2021, Monday to Sunday, 10:00 p.m to 5:00 a.m.

During the intermittent closures, at any one time, only one (1) road closure will be implemented and motorists will be diverted as follows:

 

Closure 1:

  • Motorists from Klang Town heading towards Banting will be diverted to the right-most lane and onwards to the opposite side of the road via contra flow traffic on Persiaran Tengku Ampuan Rahimah with one (1) lane made available for motorists.
  • Motorists heading towards Jalan Sri Siantan 46 will be diverted to Jalan Sri Siantan 43.

 

 

Closure 2:

  • Motorists from Klang Town heading towards Banting will be diverted to the left-most lane  on Persiaran Tengku Ampuan Rahimah with one (1) lane available for motorists.
  • Motorists from Banting heading towards Klang Town will be diverted to the left-most lane on Persiaran Tengku Ampuan Rahimah with one (1) lane available for motorists.
  • Motorists from Bulatan Simpang Lima heading towards Persiaran Seraya will be diverted to make a U-Turn opposite the Petronas petrol station before heading into Persiaran Seraya.
  • Motorists from Persiaran Seraya heading towards Banting will be diverted to Bulatan Simpang Lima before heading back on to Persiaran Tengku Ampuan Rahimah to proceed towards Banting.

The diversions are implemented following the approval from the Klang Public Works Department (JKR Klang) and Klang Municipal Council (MPK). Throughout the Conditional Movement Control Order (CMCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities. We apologise for any inconvenience caused to the public.

 

For public enquiries, please contact the LRT3 helpline at 1 800 18 2585.

 

-ENDS-

 

For media enquiries, please contact:

Lim Siew May
Media Manager, PR & Communications
MRCB George Kent Sdn Bhd
03-5033 6857
siewmay.lim@mrcbgk.com

 

ABOUT MRCB GEORGE KENT (MRCBGK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4 September 2015 as the Project Delivery Partner (PDP) of Light Rail Transit 3 (LRT3).

On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the main contractor.

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest homegrown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3) PROJECT

The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3

-->