Date | 23 November 2020 to 2 December 2020 |
Day | Monday to Sunday |
Time | 10:00 p.m. to 6:00 a.m. |
Reason | To facilitate LRT3 project-related works |
The lane closures and traffic diversions will be closed in stages at each of the locations below:
Closure A: The leftmost lanes on Jalan Langat (opposite Trio Sales Gallery, Klang-bound)
Date: 23 November 2020 to 25 November 2020
Closure B: The rightmost lane on both Klang & Banting-bound of Jalan Langat (opposite the shop lots on Jalan Gambus 2 and Trio Sales Gallery)
Date: 26 November 2020 to 28 November 2020
Closure C: The slip road on Lebuh Gambus (opposite the shop lots on Jalan Gambus 2), leftmost and middle lanes of Jalan Langat (Banting-bound)
Date: 29 November 2020 to 2 December 2020
The diversions are implemented following the approval from approval from the Klang Public Works Department (JKR Klang). Throughout the Conditional Movement Control Order (CMCO) period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.
We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding.
For more information, please contact:
Irwandy Mohd Mahayudin, Construction Manager : 012 – 3754245
Raja Nazhatul Shima binti Raja Abdul Aziz, PR & Stakeholder Management Manager : 010 – 5597979