SHAH ALAM, SELANGOR – 19 AUGUST 2021: MRCB George Kent Sdn Bhd (MRCBGK), the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be lane closures and traffic diversions on the New Klang Valley Expressway (NKVE) near the Damansara Interchange KM 17.0 (Kuala Lumpur / Sungai Buloh-bound & Shah Alam / Subang-Bound) to facilitate Segmental Box Girder (SBG) launching and LRT3 project-related works from 11:00 p.m. to 5:00 a.m. in the following stages:

 

Stage 1: The leftmost lane, slow lane and the middle lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 21 August 2021 to 10 September 2021.

During the closure, one (1) lane will be made available to motorists on NKVE Highway heading towards Kuala Lumpur / Sungai Buloh-bound as indicated on the map below:

 

 

Stage 2: The rightmost lane, middle lane and the slow lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 11 September 2021 to 20 September 2021.

During the closure, one (1) temporary lane will be made available to motorists on NKVE Highway heading towards Kuala Lumpur / Sungai Buloh-bound as indicated on the map below:

 

 

Stage 3: The rightmost lane and the middle lane (KL / Sungai Buloh-bound and Shah Alam / Subang-bound) will be closed from 21 September 2021 to 30 September 2021.

During the closure, two (2) lanes will be made available to motorists on NKVE Highway heading towards Kuala Lumpur / Sungai Buloh-bound and Shah Alam / Subang-bound as indicated on the map below:

 

 

Stage 4: The rightmost lane, middle lane and slow lane (Shah Alam / Subang-bound) will be closed from 1 October 2021 to 31 October 2021.

During the closure, one (1) lane will be made available to motorists on NKVE Highway heading towards Shah Alam / Subang-bound as indicated on the map below:

 

The diversions are implemented following the approval from Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS). Throughout the National Recovery Plan (NRP) Phase 1, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

We apologise for any inconvenience caused to the public.

For public enquiries, kindly contact the LRT3 hotline at 1 800 18 2585.

 

–END–

 

For media enquiries, please contact:

Lim Siew May

Media Manager, PR & Communications

MRCB George Kent Sdn Bhd

03-5033 6857

siewmay.lim@mrcbgk.com

 

ABOUT MRCBGEORGE KENT (MRCBGK)

MRCB George Kent Joint Venture (MRCB George Kent) was appointed on 4 September 2015 as the Project Delivery Partner (PDP) of Light Rail Transit 3 (LRT3).

On 17 October 2018, the PDP model was replaced with a fixed price contract regime, making MRCB George Kent the contractor.

MRCB is currently the largest developer cum contractor of Transit Oriented Developments (TODs) in Malaysia, while George Kent is the largest homegrown railway system specialist in Malaysia.

MRCB George Kent brings to the LRT3 project a highly-skilled and professional staff pool experienced in transit projects, with tailored and cost-effective solutions specific to Prasarana’s needs in a collaborative and supportive manner.

 

ABOUT THE LIGHT RAIL TRANSIT LINE 3 (LRT3) PROJECT

The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/ Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV. For more information, please visit www.lrt3.com.my and follow @myLRT3.

-->