Date Stage 1: 24 October 2021 to 2 November 2021

Stage 2: 3 November 2021 to 6 November 2021

Stage 3: 7 November 2021 to 8 November 2021

Stage 4: 9 November 2021 to 13 November 2021

Day Monday to Sunday
Time 10:00 p.m. to 5:00 a.m.
Reason To facilitate ‘Segmental Box Girder’ (SBG) launching and LRT3 project-related works

 

The intermittent closures and traffic diversions are as indicated on the maps below:

 

Stage 1: Slow lane closure from KM19.1 to KM18.5 (West bound), 10:00 p.m. to 1:00 a.m., followed by full closure of Ramp B heading onto Jalan Langat (Klang bound), 1:00 a.m. to 5:00 a.m. from 24 October 2021 to 2 November 2021

 

 


 

 

 

 

 

 

 

 

 

 

 

 

Stage 2: Slow and middle lane closure from KM19.1 to KM18.5 (West bound), 10:00 p.m. to 1:00 a.m., followed by full closure of Ramp B heading onto Jalan Langat (Klang bound), 1:00 a.m. to 5:00 a.m. from 3 November 2021 to 6 November 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Stage 3: Slow lane closure on Jalan Langat (Banting-bound), 10:00 p.m. to 1:00 a.m., followed by full closure from KM19.1 to KM18.5 (West bound), 1:00 a.m. to 5:00 a.m. from 7 November 2021 to 8 November 2021

 

 


 

 

 

 

 

 

 

 

 

 

 

 

Stage 4: Slow lane closure on Jalan Langat (Banting-bound), 10:00 p.m. to 1:00 a.m., followed by full closure from KM19.1 to KM18.5 (West bound) along with middle and fast lane closure from KM18.5 to KM19.1 (East bound), 10:00 p.m. to 5:00 a.m. from 9 November 2021 to 13 November 2021

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from IPD Klang Selatan (PDRM), the Klang Public Works Department (JKR Klang), Klang Municipal Council (MPK), Shah Alam Expressway – SAE (KESAS), and the Malaysian Highway Authority (MHA). Throughout the National Recovery Plan (NRP) Phase 4 period, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

Motorists are advised to drive carefully and follow the traffic signage. We apologise for any inconvenience caused to the SAE (KESAS) users.

For more information, please contact :

En. Nor Azri Omar, Project Director                                                                                                                     : 012 – 320 5736

En. Salleh Sani, Senior Manager, PR & Stakeholder                                                                                      : 019 – 253 0282

-->
Translate »