Traffic Notice: Road Closure and Traffic Diversions on Jalan Langat, Klang (between Persiaran Batu Nilam 1 and Lebuh Batu Nilam junctions, Klang/Banting bound) from 23 February 2022 to 6 March 2022
February 20, 2022
Lane Closures and Traffic Diversions nearby Damansara Interchange KM 17.0 and Ramp D (DMR1.4) (Kuala Lumpur / Sungai Buloh-Bound & Shah Alam / Subang-Bound)
February 28, 2022

Media Release: Lane closures and traffic diversions on the New Klang Valley Expressway (NKVE) near the Damansara Interchange KM 17.0 and Ramp D (DMR1.4) nearby Merchant Square (Kuala Lumpur / Sungai Buloh-bound & Shah Alam / Subang-Bound) to facilitate Segmental Box Girder (SBG) launching and LRT3 project-related works from 3 March 2022 to 31 May 2022

KUALA LUMPUR – 28 FEBRUARY 2022: Setia Utama LRT 3 Sdn Bhd (formerly known as MRCB George Kent Sdn Bhd (MRCBGK), the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be lane closures and traffic diversions on the New Klang Valley Expressway (NKVE) near the Damansara Interchange KM 17.0 and Ramp D (DMR1.4) nearby Merchant Square (Kuala Lumpur / Sungai Buloh-bound & Shah Alam / Subang-Bound) to facilitate Segmental Box Girder (SBG) launching and LRT3 project-related works from 3 March 2022 to 31 May 2022, 11:00 p.m. to 5:00 a.m. in the following stages:

Stage 1: The fast lane on Ramp D (DMR1.4) (KL / Shah Alam-bound) nearby Merchant Square will be closed from 3 March 2022 to 24 March 2022.

During the closure, one (1) lane will be made available to motorists on Ramp D (DMR1.4) heading towards KL / Shah Alam bound as indicated on the map below:

Stage 2: The rightmost lane and the slow lane on Ramp D (DMR1.4) (KL / Shah Alam-bound) nearby Merchant Square will be closed from 25 March 2022 to 8 April 2022.

During the closure, one (1) temporary lane will be made available to motorists on Ramp D (DMR1.4) heading towards KL / Shah Alam bound as indicated on the map below:

 

Stage 3: The leftmost lane, slow lane and the middle lane (KL / Shah Alam-bound) will be closed from 9 April 2022 to 23 April 2022.

During the closure, one (1) lane will be made available to motorists on NKVE Highway heading towards Shah Alam / KL-bound as indicated on the map below:

Stage 4: The rightmost lane and the middle lane (KL / Sungai Buloh-bound and Shah Alam / Subang-bound) will be closed from 24 April 2022 to 7 May 2022.

During the closure, two (2) lanes will be made available to motorists on NKVE Highway heading towards Kuala Lumpur / Sungai Buloh-bound and Shah Alam / Subang-bound as indicated on the map below:

Stage 5: The rightmost lane, middle lane and the slow lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 8 May 2022 to 20 May 2022.

During the closure, one (1) temporary lane will be made available to motorists on NKVE Highway heading towards Kuala Lumpur / Sungai Buloh-bound as indicated on the map below:

 

 

 

 

Stage 6: The leftmost lane, slow lane and the middle lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 21 May 2022 to 31 May 2022.

During the closure, one (1) lane will be made available to motorists on NKVE Highway heading towards Kuala Lumpur / Sungai Buloh-bound as indicated on the map below:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The diversions are implemented following the approval from Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS). Throughout the National Recovery Plan (NRP) Phase 4, we will be following the guidelines of the Ministry of International Trade and Industry (MITI) and the Ministry of Health (MOH) when carrying out our construction activities.

We apologise for any inconvenience caused to the public.

For public enquiries, please contact the LRT3 helpline at 1 800 18 2585.

 

ABOUT SETIA UTAMA LRT 3 SDN BHD 

(Formerly known as MRCB George Kent Sdn Bhd)

Setia Utama LRT 3 Sdn Bhd is a wholly owned subsidiary of Malaysian Resources Corporation Berhad (MRCB), the country’s pioneer Transit Oriented Developer and a leading urban property and construction company, listed on the Main Market of Bursa Malaysia Securities Berhad since 1971.

Setia Utama LRT 3 Sdn Bhd is the main contractor of the LRT3 project providing the LRT3 project with a highly skilled team experienced in transit projects, with tailored and cost-effective solutions in a collaborative and supportive manner for the project owner, Prasarana Malaysia Bhd. The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV.

 

For more information, please visit www.lrt3.com.my and follow @myLRT3.

________________________________________________________________________________

MEDIA CONTACT

Liyana Yusoff

Manager, PR & Communications

Setia Utama LRT 3 Sdn. Bhd.

(Formerly known as MRCB George Kent Sdn Bhd)

03-7688 9298

liyana@kvlrt3.com

-->
Translate »