KUALA LUMPUR – 7 June 2022: Setia Utama LRT 3 Sdn Bhd (formerly known as MRCB George Kent Sdn Bhd (MRCBGK)), the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be intermittent closures at the Pandamaran Interchange (Ramp A) from Jalan Langat heading to Kuala Lumpur, (Ramp B) from Kuala Lumpur heading to Jalan Langat and from KM18.5 to KM19.1 (both bounds) of the Shah Alam Expressway – SAE (KESAS) to facilitate railing installation and LRT3 project-related works from 9 June 2022 to 12 June 2022, 10:00 p.m. to 6:00 a.m. in the following stages:
Stage 1: Full closure of Ramp B from SAE heading to Jalan Langat (Banting bound), 10:00 p.m. to 12:00 a.m. on 9 June 2022.
During the closure, the traffic management scheme will be as indicated in the map below.
Stage 2: Full closure of Ramp B from SAE heading to Jalan Langat (Klang bound), 12:00 a.m. to 3:00 a.m., on 10 June 2022.
During the closure, the traffic management scheme will be as indicated in the map below.
Stage 3: Full closure from KM19.1 to KM18.5 of SAE (West bound), 10:00 p.m. to 2:00 a.m., from 10 June 2022 to 11 June 2022.
During the closure, the traffic management scheme will be as indicated in the map below.
Stage 4: Full closure from KM18.5 to KM19.1 of SAE (East bound), 2:00 a.m. to 6:00 a.m., on 11 June 2022.
During the closure, the traffic management scheme will be as indicated in the map below.
Stage 5: Full closure of Ramp A from Jalan Langat heading onto SAE (Kuala Lumpur bound), 10:00 p.m. to 3:00 a.m., from 11 June 2022 to 12 June 2022.
During the closure, the traffic management scheme will be as indicated in the map below.
The diversions are implemented following the approval from IPD Klang Selatan (PDRM), the Klang Public Works Department (JKR Klang), Klang Municipal Council (MPK), Shah Alam Expressway (KESAS) and Malaysian Highway Authority (MHA).
Motorists are advised to drive carefully and follow the traffic signages during the closure. We apologise for any inconvenience caused to the SAE (KESAS) users.
For public enquiries, please contact the LRT3 helpline at 1 800 18 2585.
-ENDS-
ABOUT SETIA UTAMA LRT 3 SDN BHD
(Formerly known as MRCB George Kent Sdn Bhd)
Setia Utama LRT 3 Sdn Bhd is a wholly owned subsidiary of Malaysian Resources Corporation Berhad (MRCB), the country’s pioneer Transit Oriented Developer and a leading urban property and construction company, listed on the Main Market of Bursa Malaysia Securities Berhad since 1971.
Setia Utama LRT 3 Sdn Bhd is the main contractor of the LRT3 project providing the LRT3 project with a highly skilled team experienced in transit projects, with tailored and cost-effective solutions in a collaborative and supportive manner for the project owner, Prasarana Malaysia Bhd. The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang by 2024. Developed in line with the Greater Kuala Lumpur/Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV.
For more information, please visit www.lrt3.com.my and follow @myLRT3.
________________________________________________________________________________
MEDIA CONTACT
Liyana Yusoff
Manager, PR & Communications
Setia Utama LRT 3 Sdn. Bhd.
(Formerly known as MRCB George Kent Sdn Bhd)
03- 7688 9298