KUALA LUMPUR – 23 MARCH 2023: Setia Utama LRT 3 Sdn Bhd, the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be intermittent road closures and traffic diversions on Lebuh Keluli, Shah Alam and Federal Highway 2 (Persiaran Bestari and Klang-bounds) to facilitate LRT3 project related works from 26 March 2023 to 30 September 2023 (Monday to Sunday), 10:00p.m. to 5:00a.m. at the following locations:

Closure A: The slip road on Lebuh Keluli (Federal Highway 2-bound)

During the closure, motorists will be diverted as indicated on the map below:

  • Motorists from Persiaran Bestari/Lebuh Keluli heading towards (Federal Highway (KL-bound) will be diverted onto Lorong Keluli 1a, Lorong Keluli 1c and U-turn at the traffic light junctions before heading straight onto Federal Highway (KL-bound).
  • Motorists from Persiaran Bestari/Lebuh Keluli heading towards Federal Highway (Klang-bound) will be diverted onto Lorong Keluli 1a, Lorong Keluli 1c, U-turn at traffic light junctions, head straight onto Federal Highway (KL-bound), U-turn at Persiaran Kayangan before heading onto Federal Highway (Klang-bound).
  • Motorists from Persiaran Bestari/Lebuh Keluli heading towards Federal Highway 2/Grand Sepadu Highway (Klang-bound), will be diverted onto Lorong Keluli 1a, Lorong Keluli 1c, U-turn at the traffic light junctions, head straight onto Federal Highway (KL-bound), U-turn at Persiaran Kayangan and head straight onto Federal Highway (Klang-bound) before turning right onto Federal Highway 2 towards Grand Sepadu Highway.

Closure B: The slip road closure on Lebuh Keluli (Persiaran Bestari-bound)

During the closure, motorists will be diverted as indicated on the map below:

  • Motorists from Grand Sepadu Highway heading towards Persiaran Bestari will be diverted onto Federal Highway (KL-bound), Persiaran Kayangan, Persiaran Permai and turn right onto Persiaran Bestari.
  • Motorists from Grand Sepadu Highway heading towards Lengkuk Keluli 1 will be diverted onto Federal Highway (KL-bound), Persiaran Kayangan, Persiaran Permai, turn left onto Lebuh Keluli, U-turn at the traffic light junction opposite ASAC Logistics Sdn Bhd and turn left onto Lengkuk Keluli 1.
  • Motorists from Grand Sepadu Highway heading towards Lebuh Keluli, will be diverted onto Federal Highway (KL-bound), Persiaran Kayangan, Persiaran Permai and turn left onto Lebuh Keluli.

Closure C: The rightmost lane on Federal Highway 2 (Grand Sepadu Highway-bound)

During the closure, two (2) lanes will be made available to motorists on Federal Highway 2                                          heading towards Grand Sepadu Highway as indicated on the map below:

Closure D: The middle-lane on Federal Highway 2 (Klang-bound)

During the closure, two (2) lanes will be made available to motorists from Grand Sepadu                                              Highway heading towards Federal Highway as indicated on the map below:

Closure E: The rightmost lane on Federal Highway 2 (Klang-bound)

During the closure, two (2) lanes will be made available to motorists from Grand Sepadu                              Highway heading towards Federal Highway as indicated on the map below:

The diversions are implemented following the approval from the Public Works Department (JKR) and Shah Alam Municipal Council (MBSA).

We apologise for any inconvenience caused to the public.

For public enquiries, please contact the LRT3 helpline at 1 800 18 2585 from Monday to Friday: 8.30am to 5.30pm (excluding Public Holiday).

-ENDS-

ABOUT SETIA UTAMA LRT 3 SDN BHD 

(Formerly known as MRCB George Kent Sdn Bhd)

Setia Utama LRT 3 Sdn Bhd is a wholly owned subsidiary of Malaysian Resources Corporation Berhad (MRCB), the country’s pioneer Transit Oriented Developer and a leading urban property and construction company, listed on the Main Market of Bursa Malaysia Securities Berhad since 1971.

Setia Utama LRT 3 Sdn Bhd is the main contractor of the LRT3 project providing the LRT3 project with a highly skilled team experienced in transit projects, with tailored and cost-effective solutions in a collaborative and supportive manner for the project owner, Prasarana Malaysia Bhd. The LRT3 project envisages to connect 2 million people between Bandar Utama and Klang. Developed in line with the Greater Kuala Lumpur/Klang Valley (GKL/KV) Land Public Transport Masterplan, LRT3 will be a key feature in extending rail connectivity to the Western Corridor of GKL/KV.

For more information, please visit www.lrt3.com.my and follow @myLRT3.

__________________________________________________________________________________

MEDIA CONTACT

Liyana Yusoff / Emir Shaukey Hendry

Manager / Executive – PR & Communications

Setia Utama LRT 3 Sdn. Bhd.

03-7688 9298  

prcomms@kvlrt3.com

-->