Date 5 July to 4 October 2018 Time 24 hours Duration 3 months Reason To facilitate LRT3 utilities relocation, road widening, pier column construction works and guideway launching works at Persiaran Kerjaya (from Masjid An-Nur Temasya until Accentra Glenmarie) SHAH ALAM, SELANGOR – 4 July, 2018: MRCB George Kent, the Project Delivery Partner (PDP) of the Light Rail Transit 3
Read More
SHAH ALAM, 25 May 2018: MRCB George Kent Sdn Bhd (MRCBGK), the Project Delivery Partner (PDP) of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be a traffic diversion at the traffic light near Devi Sri Maha Karumariammam Temple at Persiaran Tengku Ampuan Rahimah. This diversion will start from 26 May 2018 to 31 August
Read More
Date 23 June 2018 to 8 September 2018 Time 24 Hours Duration 78 days Reason To facilitate LRT3 bore piling works and water pipe relocation Package GS07-008 SHAH ALAM, 22 June 2018: MRCB George Kent, the Project Delivery Partner (PDP) of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be continuation of lane diversions in front of
Read More
Please be informed that with approval from Majlis Perbandaran Klang and Jabatan Kerja Raya, there will be continuation of lane diversions along Jalan Meru, Klang, to facilitate LRT3 bore pilings works and water pipe relocation from 23 June 2018 (Saturday) until 8 September 2018 (Saturday) for duration of 78 days. Lane diversions along Jalan Meru, Klang (24-hour) The lane diversions
Read More