Date 16 to 17 March, 22 to 24 March, 29 to 31 March 2019 Time 10:00 p.m. to 5:00 a.m. Duration 3 weekends Reason To facilitate steel cage installation and concrete casting works for LRT3 project. SHAH ALAM, 11 March 2019: MRCB George Kent Sdn Bhd (MRCBGK), the contractor of the Light Rail Transit 3
Read More
Merujuk kepada kelulusan dari pihak Jabatan Kerja Raya (JKR), dimaklumkan bahawa kerja-kerja pemasangan tetopi tiang sambut akan dijalankan di sebahagian Persiaran Tengku Ampuan Rahimah, Klang pada 15 sehingga 30 Mac 2019, bermula dari jam 10.00 malam sehingga 5.00 pagi. Lorong kanan bagi kedua-dua arah di Persiaran Tengku Ampuan Rahimah juga akan ditutup dari jam 10.00 malam sehingga 5.00 pagi secara
Read More
Date 15 to 30 March 2019 Time 10:00 p.m. to 5:00 a.m. Duration 15 nights Reason To facilitate pier cap launch for the LRT3 project. SHAH ALAM, 11 March 2019: MRCB George Kent Sdn Bhd (MRCBGK), the main contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be traffic
Read More
Please be informed that there will be a traffic diversion near Bulatan Simpang Lima on Persiaran Tengku Ampuan Rahimah, Klang to facilitate piling, pile cap and pier works for the LRT3 project starting from 11 March until 10 September 2019 for 24 hours daily. The traffic diversion is as follows: The left lane near Bulatan Simpang Lima (Sri Andalas-bound)
Read More