Tarikh 15 Ogos 2021 sehingga 17 Ogos 2021 Hari Ahad hingga Selasa Tempoh masa 11:00 malam hingga 5:00 pagi Tujuan Untuk memudahkan kerja-kerja pelancaran “U-Girder” dan kerja-kerja yang berkaitan dengan projek LRT3 Berikut adalah peta yang menunjukkan penutupan jalan dan lencongan trafik: Kerja-kerja ini akan dilaksanakan dengan kelulusan dari Jabatan Kerja Raya Daerah Petaling (JKR Petaling) serta mengikuti garis
Read More
SHAH ALAM, SELANGOR – 12 AUGUST 2021: MRCB George Kent, the contractor of the Light Rail Transit 3 (LRT3) project, wishes to inform that there will be road closures and traffic diversions on Persiaran Kerjaya from EON Berhad to the Caltex junction (both Shah Alam and Kuala Lumpur / Subang-bound) to facilitate ‘U-Girder’ launching and LRT3 project-related works from
Read More
Date 16 August 2021 to 20 August 2021 Day Monday to Sunday Time 11:00p.m. to 5.00a.m. Reason To facilitate I-beam launching works The closure and traffic diversion are as shown on the map below: The diversions are implemented following the approval from the Petaling Public Works
Read More
Tarikh 16 Ogos 2021 hingga 20 Ogos 2021 Hari Isnin hingga Ahad Tempoh masa 11:00 malam hingga 5:00 pagi Tujuan Untuk memudahkan kerja-kerja pelancaran “I-beam” Berikut adalah peta yang menunjukkan penutupan laluan dan lencongan trafik tersebut: Kerja-kerja ini akan dilaksanakan mengikut kelulusan daripada Jabatan Kerja Raya
Read More