Date1 March 2024 to 31 May 2024
DayMonday to Sunday
Time11:00 p.m to 5:00 a.m
ReasonTo facilitate LRT3 project-related works

The closures and diversions will be done in stages as shown on the maps below:

Stage 1: The leftmost lane and slow lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 1 March 2024 to 16 March 2024. 

Stage 2: The leftmost lane and the middle lane (Kuala Lumpur / Subang Toll-bound) will be closed from 17 March 2024 to 7 April 2024.

Stage 3: The leftmost lane, slow lane and middle lane (Kuala Lumpur / Shah Alam-bound) will be closed from 8 April 2024 to 30 April 2024.

Stage 4:  The rightmost lane and the middle lane (KL / Sungai Buloh-bound and Shah Alam / Subang-bound) will be closed from 1 May 2024 to 31 May 2024.

The diversions are implemented following the approval from the Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS).

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For more information, please contact:

Mohamad Rasydi Awang Chik, Senior Project Manager                                                       : 011-10404515

Salmi Azuriza Che Ali, Senior Executive, PR & Stakeholder Management                             : 012- 6546905

-->
Translate »