Please be informed that there will be closure on the most left lane along Persiaran Dato’ Menteri (SIRIM bound) for 4km and the most left lane along Persiaran Tasik (Pusat Bandar Shah Alam bound) for 500m due to the piloting work for Light Rail Transit 3 (LRT3) from 1 February (Thursday) to 15 February (Thursday) 2018.

The piloting work is planned to start at 9:00 p.m. and is expected to be completed on the next day at 6:00 a.m with normal traffic flow restored before peak traffic hours in the morning for fourteen (14) consecutive nights and will be executed with immediate effect at the associated locations.

Lane Closure 1:
The most left lane near Persiaran Dato’ Menteri will be closed 4km after the entrance of Pejabat Pos Besar Shah Alam until PKNS Open Carpark.

Lane Closure 2:
The most left lane will be closed 500m near Persiaran Tasik intersection towards Pusat Bandar Shah Alam.

Below is a map indicating the lane closure near Persiaran Dato’ Menteri and Persiaran Tasik:

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and
patience as we build LRT3 for the betterment of the future and in improving Klang Valley’s public transport system.

For more information :
Rashid Ibrahim, Project Manager : 019 2973889
Nur Adlina Abu Bakar, Assistant Manager, PR & Stakeholder Management : 012 6899677

-->