Date 15 July 2022 to 30 September 2022
Day Monday to Sunday
Time 11:00 p.m to 5:00 a.m
Reason To facilitate Segmental Box Girder (SBG) Launching and LRT3 project-related works

The closures and diversions will be done in stages as shown on the maps below:

Stage 1: The fast lane on Ramp D (DMR1.4) (KL / Shah Alam-bound) nearby Merchant Square will be closed from 15 July 2022 to 24 July 2022.

Stage 2: The rightmost lane and the slow lane on Ramp D (DMR1.4) (KL / Shah Alam-bound) nearby Merchant Square will be closed from 25 July 2022 to 31 July 2022.

Stage 3: The leftmost lane, slow lane and the middle lane (KL / Shah Alam-bound) will be closed from 1 August 2022 to 15 August 2022.

Stage 4: The rightmost lane and the middle lane (KL / Sungai Buloh-bound and Shah Alam / Subang-bound) will be closed from 16 August 2022 to 31 August 2022.

Stage 5: The rightmost lane, middle lane and the slow lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 1 September 2022 to 15 September 2022.

Stage 6: The leftmost lane, slow lane and the middle lane (Kuala Lumpur / Sungai Buloh-bound) will be closed from 16 September 2022 to 30 September 2022.

The diversions are implemented following the approval from the Lembaga Lebuhraya Malaysia (LLM) and Projek Lebuhraya Usahasama Berhad (PLUS).

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For more information, please contact:

Yap Kok Fong, Senior Project Manager                                                                                                                       : 012-5082908

Salmi Azuriza Che Ali, Senior Executive, PR & Stakeholder Management                                             : 012- 6546905

-->
Translate »