Date3 April 2023 to 15 April 2023
DayMonday to Sunday
Time11:00 p.m. to 5:00 a.m.
ReasonTo facilitate LRT3 project-related works

The road closures and traffic diversions are as shown on the map below:

Stage 1: Left-lane on Persiaran Kerjaya (Shah Alam-bound) before LRT2 Glenmarie junction and both lanes on Persiaran Kerjaya (Shah Alam-bound) from LRT2 Glenmarie junction to Temasya 8 heading towards Shah Alam will be closed from 3 April 2023 to 4 April 2023.

Stage 2: Left-lane on Persiaran Kerjaya (Shah Alam-bound) before LRT2 Glenmarie junction, left lane at the traffic light junction on Persiaran Kerjaya, opposite Glenamrie Garden and both lanes on Persiaran Kerjaya (Kuala Lumpur / Subang-bound) from Caltex until LRT2 Glenmarie junction heading towards Kuala Lumpur / Subang will be closed from 5 April 2023 to 6 April 2023.

Stage 3: Both lanes at the traffic light junction on Persiaran Kerjaya opposite DRB-Hicom, all lanes on Persiaran Kerjaya nearby EON Berhad until LRT2 Glenmarie junction (both Shah Alam and Subang/Kuala Lumpur-bound), right-lane on Jalan Pengaturcara U1/51 (Kuala Lumpur /Subang-bound) and right-lane on Persiaran Kerjaya (Shah Alam-bound) before LRT2 Glenmarie will be closed from 7 April 2023 to 15 April 2023.

The diversions are implemented following the approval from the Jabatan Kerja Raya Daerah Petaling (JKR Petaling).

We apologise for any inconvenience caused to the public and greatly appreciate your kind understanding and patience as we build LRT3 for the betterment of the future.

For more information, please contact:

Mohamad Rasydi Awang Chik, Project Manager                                                          : 011-10404515

Salmi Azuriza Che Ali, Senior Executive, PR & Stakeholder Management                    : 012- 6546905

-->